Associated content: 
Sub-categories: 

2013 AV-6 Pre-CST overview at DFRC

2013 AV-6 AVAPS Monitoring during Pre-CST (7.29.13)

AV-6 Outdoor Inst. and Satcom Testing with WFF (07.25.13)

HS3 07/26/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Pending:  new camera lens for nose camera

AV-6 Completed:

Friday July 26 - In-hangar IT/comm troubleshooting

AV-6 Planned:

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 0700 PDT

 

WFF UPDATE:

AV-6 Completed:

2013 AV-6 AVAPs final inspection for preCST (7.26.13)

HS3 07/25/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Thursday July 25 - removed EIPs 1/6 for firmware update

Pending:   new camera lens for nose camera, EIP firmware

AV-6 Completed:

Thursday July 25 - Outdoor Payload-IT testing and in-hangar troubleshooting

AV-6 Goals:

Friday July 26 – IT/Comm troubleshooting, 0600-1430 (no PI's needed)

HS3 07/24/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

HIWRAP Battery switch

Pending:   new camera lens for nose camera.

AV-6 Completed:

Wednesday July 24 - Outdoor Payload-IT testing

Goals:

Thursday July 25 – Continue Outdoor Payload-IT testing, 0600-1430  (PIs needed at 0700)

 

WFF UPDATE

HS3 Google Hangout (07.23.13)

AV6 PIs in GHOC-E (07.23.13)

HS3 07/23/13 Daily Schedule

DFRC UPDATE:  

AV-1 

Pending: HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Tuesday July 23 - Initial Outdoor Payload-IT testing.

Goals:

Wednesday July 24 – Continue Outdoor Payload-IT testing, 0600-1430  (PIs needed at 0700)

 

WFF UPDATE

AV-6 Completed:

Pages

Subscribe to RSS - HS3