HS3 07/26/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Pending:  new camera lens for nose camera

AV-6 Completed:

Friday July 26 - In-hangar IT/comm troubleshooting

AV-6 Planned:

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 0700 PDT

 

WFF UPDATE:

AV-6 Completed:

Friday July 26 - IT/Comm testing 

AV-6 Planned:

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 1000 EDT