HS3 07/23/13 Daily Schedule

DFRC UPDATE:  

AV-1 

Pending: HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Tuesday July 23 - Initial Outdoor Payload-IT testing.

Goals:

Wednesday July 24 – Continue Outdoor Payload-IT testing, 0600-1430  (PIs needed at 0700)

 

WFF UPDATE

AV-6 Completed:

Tuesday July 23 -  COMSEC Brief 0900,  Initial Outdoor Payload-IT testing.

AV-6 Goals:

Wednesday July 24 -  Continue Outdoor Payload-IT testing, 1000-1730

PAO/EPO

DFRC HS3 Teachers Workshop 7/15-25

Chincoteague Pony Swim 7/24 & 7/26 *corrected dates (beware of tourist traffic)