HS3 07/22/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Monday July 22 - Outside testing for Ku comms and intercoms.

Goals:

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Monday July 22 – Wt & Balance and fueling

Goals:

Tuesday July 23 - Initial Outdoor Payload-IT testing, 0600-1430  (PIs needed at 0800)

AV6 ready to fuel and AV1 outdoor testing (07.22.13)

Airborne Detector for Energetic Lightning Emissions

The Airborne Detector for Energetic Lightning Emissions (ADELE) detects gamma-rays and relativistic electrons associated with lightning and thunderstorm charging. The primary scientific target is terrestrial gamma-ray flashes (TGFs), brief (< 1 millisecond), extremely bright bursts of high energy radiation that have mostly been detected from satellites in low Earth orbit. TGFs are usually simultaneous with intra-cloud lightning, but only a small fraction of these lightning flashes seem to produce them. The cause of TGFs, their connection with lightning, and whether they are frequent enough to be a radiation hazard to airline passengers and crew are all unanswered questions.

ADELE is designed to study these events from close to their production site, where the signal can be much more intense than it is for the satellites 600 km away from the storm. On the AV-1 Globak Hawk in HS3, ADELE will pass above and near electrified storms in both the eyewall and rainband regions.  ADELE uses three scintillation detectors -- 5" and 1" diameter plastic scintillators and a 3" diameter lanthanum bromide scintillator.  The plastic detectors provide the ability to measure extremely high count rates without saturation, and the lanthanum bromide detector provides improved spectroscopic information on the energy distribution of the gamma rays.  All three detectors are enclosed in a single box in the interior of the Global Hawk, since the gamma radiation (100 keV up to about 50 MeV) is highly penetrating.

Point(s) of Contact: 

HS3 07/20/13 Daily Schedule

DFRC UPDATE:  

AV-1

Goals:

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Saturday July 20 – CPL and AVAP powered in hangar.

Goals:

Sunday July 21 – HARD DOWN DAY

AV-6 AVAPS Integration (07.19.13)

AV-1 ADELE Gamma-source Calibration (07.19.13)

HS3 07/19/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Friday July 19 – PI Instrument backbone test.

Goals:

Friday July 19 – Indoor power-on testing in afternoon

Saturday July 20  – PIs travel home.  Return Aug 4.  Ops begin Aug 5.

Sunday July 21 – HARD DOWN DAY

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

2013 AV-1 Satcom Testing to WFF from DFRC (07.18.13)

2013 AV-6 SHIS fully integrated (07.18.13)

2013 HIRAD AV-1 installation started