HS3 07/25/13 Daily Schedule

DFRC UPDATE:  

AV-1 Completed:

Thursday July 25 - removed EIPs 1/6 for firmware update

Pending:   new camera lens for nose camera, EIP firmware

AV-6 Completed:

Thursday July 25 - Outdoor Payload-IT testing and in-hangar troubleshooting

AV-6 Goals:

Friday July 26 – IT/Comm troubleshooting, 0600-1430 (no PI's needed)

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 0700 PDT

 

WFF UPDATE:

AV-6 Completed:

Thursday July 25 -  Outdoor Payload-IT testing 

AV-6 Goals:

Friday July 26  -  IT/Comm troubleshooting, 0900-1730 (no PI's needed)

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 1000 EDT