HS3 07/19/13 Daily Schedule
DFRC UPDATE:
AV-1 Completed:
Friday July 19 – PI Instrument backbone test.
Goals:
Friday July 19 – Indoor power-on testing in afternoon
Saturday July 20 – PIs travel home. Return Aug 4. Ops begin Aug 5.
Sunday July 21 – HARD DOWN DAY
Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)
Pending: HIWRAP Battery switch, new camera lens for nose camera.
AV-6 Completed:
Friday July 19 – Final integration.
Goals:
Saturday July 20 – Power-on inside the hangar 0700-1200
Sunday July 21 – HARD DOWN DAY
Monday July 22 – Wt & Balance and fueling
Tuesday July 23 - Initial Outdoor Payload-IT testing, 0800-1430
The Ku system at Wallops will be used for the testing on Monday and Tuesday.
WFF UPDATE:
AV-1 Completed:
Friday July 19 – PI Instrument backbone.
Goals:
Saturday July 20 – PIs travel home. Return Aug 4. Ops begin Aug 5.
AV-6 Goals:
Sunday July 21 - PIs travel. Prep begins July 22
Monday July 22 – Wt & Balance and fueling; PIs set up / computer scans etc.
Tuesday July 23 - Initial Outdoor Payload-IT testing, 1100-1730