GHOST Engineers (Neil Humpage, Andy Vick) test instrument (2.20.15)

ATTREX 02/20/15 Mission Daily Schedule

Overview:

  • Instruments and aircraft ready for CST on Monday, Flight on Tuesday
  • Note to all Inst. PI’s – please see GHOC show schedule below

Accomplishments:

MMS Nav data wiring change (2.19.15)

ATTREX 02/19/15 Mission Daily Schedule

Overview:

  • Maintenance and Avionics aircraft work continues in preparation for CST
  • CST scheduled – however, all PI’s should look for e-mail at 0800 confirming details

Accomplishments:

  • Maintenance and avionics flight readiness activity continues on aircraft
  • AIITS removed for upload and checkout of new software
  • MMS Nav-data cable modified to reduce noise

Issues/Watch items:

GHOST PIs fill LN2 prior to outdoor testing (2.18.15)

ATTREX 02/18/15 Mission Daily Schedule

Overview:

  • Pre-CST related activity performed – ready for CST Friday.
  • Air vehicle readiness and instrument integration/testing is on schedule.

Accomplishments:

ATTREX 02/04/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Z-25 installation is behind schedule due to a delay in pallet prep, however the pallet is expected tomorrow.
 
Accomplishments:

  • All Instruments have passed SIL Bench Testing.
  • AIITS Pod completes Environmental Testing
  • MMS, MPT, Hawkeye, NWV, O3, and GWAS are mechanically installed.
  • AIITS fiber installed – Cabin Pres. Test Thursday AM

Concerns / Watch List:

ATTREX 02/05/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Installation is 2 days behind schedule… currently the only instrument not mounted.
 
Accomplishments:

  • Cabin Pressurization test completed
  • Avionics tie-up of harnesses ongoing
  • AIITS Pod mounted on the wing, preloads almost completed
  • CAST/ATTREX Leads Status/Flight Planning telecom held
  • Final pre-installation work on the GHOST Pallet continuing

Concerns / Watch List:

ATTREX 02/06/15 Mission Daily Schedule

Overview:

  • CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25 
  • GHOST installation continues Saturday

Accomplishments:

  • AIITS Pod mounting on the wing completed
  • Structural Shear/Bending Analysis review meeting held at NGC
  • Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.

Concerns / Watch List:

ATTREX 02/10/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.
 
Accomplishments:

  • GHOST mechanical installation completed (see pic)
  • AIITS Pod structural dynamics (“Ping”) test completed (see pic)

Concerns / Watch List: