ATTREX 02/10/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.
 
Accomplishments:

  • GHOST mechanical installation completed (see pic)
  • AIITS Pod structural dynamics (“Ping”) test completed (see pic)

Concerns / Watch List:

  • AIITS replacement Diode Laser - delivery expected tomorrow.
  • Cannot locate 2nd MMS EIP Harness. OA may need to fabricate a replacement.
  • NGC Shear/Bending analysis – holding for new NGC analysis using updated model.

Upcoming Schedule:

  • Tomorrow, Wednesday:
    • CAST/ATTREX Leads Telecom at 0800 PST
    • Hawkeye Harness end-to-end checks (Zone-3 and Pod)
    • MMS EIP Harness review (Zone-7)
    • GHOST ATR Ping Setup and Test
    • GHOST Harness installation (after Ping Test, time permitting)
  • Thursday:
    • Weight & Balance by NGC Engr.
    • Data-IT Testing in Hangar (time permitting)