Overview:

  • CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25 
  • GHOST installation continues Saturday

Accomplishments:

  • AIITS Pod mounting on the wing completed
  • Structural Shear/Bending Analysis review meeting held at NGC
  • Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.

Concerns / Watch List:

  • AIITS Diode Laser replacement has been shipped – expected at AFRC on Monday
  • Reviewing need for laser-replacement waiver
  • NGC Shear/Bending analysis by NGC now suspected to be in error, analysis to be corrected
  • GHOST integration continues Saturday to get on schedule

Upcoming Schedule:

  • Tomorrow, Saturday: GHOST Pallet installation continues
  • Monday:
    • GHOST avionics harness installation
    • Begin Data-IT Hangar Testing of all instruments on aircraft power