ATTREX 02/06/15 Mission Daily Schedule
Overview:
- CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25
- GHOST installation continues Saturday
Accomplishments:
- AIITS Pod mounting on the wing completed
- Structural Shear/Bending Analysis review meeting held at NGC
- Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.
Concerns / Watch List:
- AIITS Diode Laser replacement has been shipped – expected at AFRC on Monday
- Reviewing need for laser-replacement waiver
- NGC Shear/Bending analysis by NGC now suspected to be in error, analysis to be corrected
- GHOST integration continues Saturday to get on schedule
Upcoming Schedule:
- Tomorrow, Saturday: GHOST Pallet installation continues
- Monday:
- GHOST avionics harness installation
- Begin Data-IT Hangar Testing of all instruments on aircraft power