ATTREX 02/18/15 Mission Daily Schedule

Overview:

  • Pre-CST related activity performed – ready for CST Friday.
  • Air vehicle readiness and instrument integration/testing is on schedule.

Accomplishments:

  • Outdoor Satcom testing, including Pre-CST related testing
  • GHOST Cryostat LN2 fill performed on aircraft outdoors
  • Rehearsal for pre-Engine Start LN2 fill on flight days
  • GHOST TAM alignment measurements performed
  • AIITS troubleshooting software updates

Issues/Watch items:

  • MMS reports some noise on LN-100 nav data line; troubleshoot tomorrow
  • Wallops Ku Ground Station pointing issue unresolved; support from WFF requested

Upcoming Schedule:

Thursday: Maint and Avionics aircraft final prep for CST
Friday: All personnel participate in CST; Schedule TBA
Saturday: Support in Payload Cage for PIs as needed, no aircraft access