ATTREX 02/04/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Z-25 installation is behind schedule due to a delay in pallet prep, however the pallet is expected tomorrow.
 
Accomplishments:

  • All Instruments have passed SIL Bench Testing.
  • AIITS Pod completes Environmental Testing
  • MMS, MPT, Hawkeye, NWV, O3, and GWAS are mechanically installed.
  • AIITS fiber installed – Cabin Pres. Test Thursday AM

Concerns / Watch List:

  • AIITS Diode Laser replacement arrival by early next week.
  • Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
  • GHOST Pallet installation is behind schedule – expected to begin tomorrow
  • NGC Shear/Bending analysis - Meeting at NGC on Friday to discuss status

Upcoming Schedule:

  • Tomorrow, Thursday:
    • 0800 CAST/ATTREX Proj. Lead Telecom
    • Cabin Pressurization Test
    • Continue Avionics tie-up of harnesses
    • AIITS Pod Installation
    • GHOST Pallet installation
  • Friday / Saturday:
    • Finish GHOST Installation
    • Aircraft Wt. & Balance (day/time TBD)