Synonyms: 
KORUS-AQ (HL 5200)
Associated content: 

KORUS-AQ 04/05/16 Mission Daily Schedule

PLAN FOR 4/5

0700 - 1700: Instrument Integration SAGA, HR-AMS, CAMS, LARGE, DIAL, K-AMS, K-CCN, K-SP2, PTR-MS

KORUS-AQ 04/04/16 Mission Daily Schedule

PLAN FOR 4/4

KORUS-AQ 04/03/16 Mission Daily Schedule

PLAN FOR 4/3

KORUS-AQ 04/02/16 Mission Daily Schedule

PLAN FOR 4/2

KORUS-AQ 04/01/16 Mission Daily Schedule

PLAN FOR 4/1

0700 - 1700: Instrument Integration: SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2, AMS, K-AMS, K-CCN, K-SP2

END OF THE DAY REPORT:

KORUS-AQ 03/31/16 Mission Daily Schedule

PLAN FOR 3/31

0700 - 1700: Instrument Integration: SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2, AMS, K-AMS

End of the Day Report:

KORUS-AQ 03/30/16 Mission Daily Schedule

PLAN FOR 3/30: 
Instrument Integration: SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2

3/30 End of the Day Report:
DLH: Up and running. DACOM/COLAS powering up this afternoon. Cylinders ready to be installed. 
DIAL: On schedule. Power check planned for Thursday.
SAGA: On schedule.
LARGE: Ready for install tomorrow.
HD-SP2: Arrived today. Expecting instrument to arrive tomorrow. 

NEW ARRIVALS:
AMS and K-AMS (both shipments delivered today. Teams unpacking)

KORUS-AQ 03/29/16 Mission Daily Schedule

PLAN FOR 3/29
Instrument Integration: ATHOS, SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2

KORUS-AQ 03/28/16 Mission Daily Schedule

TODAY'S PROGRES REPORT
SAGA arrived on site.
DLH/DACOM/COLAS:  Pump installed. Power check to be completed by this afternoon or tomorrow morning.
DIAL: On schedule.
NOxyO3: On schedule. Team departed on 3/25 to return next week.
LARGE: Populating rack. Scheduled to go on the plane Wednesday.

NOTE:
Egress training for all future flyers is given weekly every Wednesday and Thursday after the 1pm day debrief.

KORUS-AQ 03/25/16 Mission Daily Schedule

Update:
Shakedown flight now scheduled for April 15th
Science check flight(s) scheduled for the week of April 18th.