HIRAD Installation #1 (2012)
HIWRAP fairing final fit work (2012)
AV6 ready for range flight (2012)
S-HIS inlet exhaust installed (2012)
HS3 08/31/12 Daily Schedule
WFF:
Saturday, 9/1
AV-6 – We are announcing a one day slip in transit due to a delay in receiving an FAA approved COA.
Transit is now scheduled for Sept 5 to 6.
AV-1 power is on and ACPS testing is underway.
Transit is still scheduled for Sept 17 to 18.
The calendar will be updated to reflect the changes soon.
http://espo.nasa.gov/missions/hs3/hs3-calendar/2012-09
HS3 08/30/12 Daily Schedule
WFF:
Thursday, 8/30
Successful Pilot Proficiency Flight (1hr)
AV-6 transit is on schedule for Sept 4 to 5th.
There have been some changes to the AV-1 schedule.
The calendar will be updated to reflect the changes soon.
Have a good weekend.
HS3 08/29/12 Daily Schedule
HS3 Dryden Plan of the week!
Wednesday, August 29, 2012
The landing gear issue was fixed today due to the hard work of the crew!
HS3 08/28/12 Daily Schedule
HS3 Dryden POD
Tuesday, August 28, 2012
After takeoff the landing gear gave a false indication on the gear status.
This resulted in us flying for several hours to burn off fuel before landing.
Wednesday, August 29, 2012
The crew will need to troubleshoot the landing gear. If instrument
access is needed before the next range flight, PIs should be available
in the hangar in the morning.
HS3 08/27/12 Daily Schedule
HS3 Dryden POD 2012-08-28