FIREX-AQ 06/06/19 Mission Daily Schedule
Thursday, 6/6, Accomplishments:
OPALS team performed probe fit check
ACES/IWAS rack installed
TOGA continued working on sampling lines between inlet and instrument
DIAL team made good progress
mini-DOAS team performed in-lab calibrations
NO LIF instrument removed from rack; to be reinstalled on the 18th
Friday, 6/7, Plans:
06:00 A/C Access
MASTER to load aft pit
Instrument integration tasks
13:00 Lab meeting
17:30 A/C access ends
Send pressure system schematics to Richard Wong
Send heater system schematics to Paul Martinez/Brennan Wehr