KORUS-AQ 03/29/16 Mission Daily Schedule

PLAN FOR 3/29
Instrument Integration: ATHOS, SAGA, DLH/DACOM/COLAS, DIAL, LARGE, HD-SP2

3/29 End of the Day Report:
ATHOS: Fully installed, up & running, calibrated. Team will depart tomorrow and return on April 14.
DLH: Up and running. DACOM/COLAS powering up this afternoon. Cylinders ready to be installed. Team will depart tomorrow and return April 13.
DIAL: On schedule. Power check planned for Thursday.
SAGA: On schedule.
LARGE: Ready for install tomorrow.
HD-SP2: Arrived today. Expecting instrument to arrive tomorrow. 

NOTE: Some shipping issues with USPS. If at all possible use UPS or FedEX for shipments to AFRC Palmdale.

KORUS-AQ Calendar has been updated (April):

  • Shakedown flight
  • Science Check flight
  • Safety Stand down (aircraft crew only)
  • Aircraft and Lab access

Calendar:
https://espo.nasa.gov/home/korus-aq/calendar/2016-04