HS3 07/25/14 Daily Schedule
Overview:
AV-1 Integration/Test completed on schedule – ready for CST-prep on 11Aug
AV-6 Integ. on schedule – Outdoor Satcom testing w/WFF starts Monday
Today’s Accomplishments:
AV-1 Science Integ/Test activity ends
o HIWRAP data-file download
o Aircraft jacked for gear maint. (pic)
o Science Flight-prep starts: Monday, 11Aug (see below note)
AV-6 Wt & Balance
o CPL power harness expanded to EIP-4
o CPL Testing completed
Completed Daylight Nose Cam relocation
The Plan for Saturday:
AV-6 Avionics harness tie-down activity, No Power on Aircraft
Outlook:
Monday @ AFRC: AV-6 Outdoor Testing (all times PDT):
o 0600 – 0900: Aircraft fueling
o 1000 – 1200: Power-on, Data-IT Network/System Configuration
o 1200 – ~1430: PI’s support Satcom Testing of Inst’s w/GHOC-E
Monday @ WFF: AV-6 Support in GHOC-E (all times EDT):
o 0830: Badging, if needed
o 0900: Scan Laptops, if required
o 0930: COMSEC Briefing
o 1000: Software download/install, if required
o 1200: Lunch (yum)
o 1400 – 1500: Be available (in case IT ready to start Satcom early)
o 1500 - ~1730: PI’s in GHOC-E for Inst. Satcom Testing
Tues-Wed: Continue outdoor testing w/GHOC-E
Thurs: Pre-CST
Monday Aug-11th – Special Note to AV-1 Teams:
o AFRC: 0630 PDT: HIRAD req’d for Install in GH Hangar
0800: HAMSR & HIRAD PI’s Support Data-IT Retest (HIWRAP too, if desired)
o WFF: Need to AV-1 PI’s TBD (AFRC Testing may only be in Hangar)
Continue to monitor this Daily Msg. for info