HS3 07/24/14 Daily Schedule
Overview:
AV-1 and AV-6 integration and testing is on schedule.
Today’s Accomplishments:
AV-1 HIRAD RF Test complete
o HIWRAP waveform refinement activity
o HIRAD & HAMSR removal for camera work & A/C maint.
AV-6 Hangar IT Testing
o AVAPS Testing complete
o S-HIS Testing complete
o CPL Installed and Testing in work
H.S. Student visit
The Plan for Friday (all times PDT):
AV-6 Wt. & Balance
o AV-6 Hangar IT Testing (CPL) in PM
AV-1 HIWRAP testing (PI request)
o Camera Data-IT Testing
Outlook:
Saturday Avionics activity on AV-6 (No Power on Aircraft)
Monday @ AFRC: AV-6 Outdoor Testing
o Schedule TBD (PIs should be present starting at 0830)
Monday @ WFF:
o 0730: Badging, if needed
o 0800: Scan Laptops
o 0930: COMSEC Briefing
o 1000 – 1100: Software Downloads/installs, if required
o 1100 – 1130: Eat Lunch
o 1130: Begin Satcom Testing in GHOC-E
Special Monday Aug-11th Note to AV-1 Teams:
o AFRC: 0630 Outdoor Testing of aircraft (PI’s support req’d)
o WFF: 0930 GHOC-E Support (HIRAD, HIWRAP, HAMSR PI’s needed)