ATTREX 01/14/14 Daily Schedule

ATTREX GH Overview:

  • ATTREX Instruments Ready for final pre-flight procedures.
  • A/C To PMOF (Guam) Comm Testing Guam successfully accomplished on Jan 9th.
  • ATTREX air cargo picked up. ETA to Guam: Jan 16th and at AAFB: Jan 17th.

Today's Accomplishments:

  • A/C To GMOF (Guam) Comm Testing Conducted.
  • T-1 Brief. Some open items identified and pending to be closed by T-0 briefing tomorrow.

Plans for Wednesday, Jan 15 (@ DFRC):

1000  A/C Power On. Instrument teams have aircraft access.

1300  Hands off / Power Off

1500  Aircraft Roll Out

1600  T-0 Briefing

1645  Instrument teams to GHOC

(User packets will go straight to Guam. Presence in GHOC desired for any questions/troubleshooting by IT prior to launch.)

1700  Engine Starts

1800  Take Off

TRANSIT FLIGHT PLAN: 

  • TAKE OFF: from DFRC on Wednesday, Jan 15th, 1800 PST / Thursday, 16th, 1200 ChST (Guam)
    • GHOC Staffing @ DFRC at 1645 PST for instrument teams
    • PMOF Staffing in Guam at 1000 ChST for all Instrument Teams
  • LANDING:  in Guam on Friday, Jan 17th, 0800 CHST / Thursday, Jan 16th 1400 PST