HS3 07/17/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue

 

Today’s Accomplishments:

AV-1 Wt & Balance performed

Fueling performed

Avionics prepping for power

 

The Plan for tomorrow (Friday) is:

Continue avionics prep for power (estimated 1-3 hours beginning 0630)

Power to instruments and hangar IT testing of instruments (remainder of day)

 

Outlook:

No activity planned for Saturday or Sunday

Monday +: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instrument

Monday +: AV-6 Instrument Teams arrive, Integration activity

 

Excepting Monday, AV-1 outdoor testing will start early (0630) in the morning (to stay cool).

 
Check the next Daily Status for a start time for Monday.