HS3 07/16/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

AV-1 integration activity is complete

o   HAMSR installed

o   HIRAD installed

o   HIWRAP installed

Aircraft ready for Wt. & Balance


The Plan for tomorrow (Thursday) is:

0730: Payload Cage meeting of Leads and PI’s

Wt & Balance

Fuel aircraft and reweigh

Avionics prep for power (see Friday)

Instrument teams requested to remain in Hangar to support Avionics activity

 

The Plan for Friday is:

Hangar IT Testing of instruments (0700 - 1500)

 

Outlook:

No activity planned for Saturday or Sunday

Monday +: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instrument

Monday +: AV-6 Instrument Teams arrive, Integration activity