HS3 07/14/14 Daily Schedule
Overview:
HS3 ‘14 begins today at AFRC and WFF.
Today’s Accomplishments:
Dana Tanks arrived at WFF
At AFRC, HIWRAP, HIRAD, and HAMSR teams arrived and began pre-integration testing
o HAMSR passed SIL Bench
o HIRAD SIL Bench started
COMSEC Training of PI’s at AFRC
The Plan for tomorrow (Tuesday):
0730 Payload Cage meeting of Leads and PI’s
HAMSR installation on aircraft
HIRAD outdoor sky radiation test
HIRAD completes SIL Testing, possible installation
HIWRAP SIL Bench Test
The Plan for Wednesday:
Installation of HIWRAP and HIRAD
Begin Hangar IT if time allows
Prep aircraft for Wt./Bal
Outlook:
Thursday AM is AV-1 Wt/Balance
Thursday PM is Hangar IT with all instruments
Friday all day: Hangar IT with all instruments