ATTREX 02/16/14 Daily Schedule

ATTREX  GH Overview:

 -Instrument and Aircraft have been preflighted

 -Next Flight is tomorrow, Monday, 17Feb.

 o   Take-off 0300 ChST, (1700 Z Sunday, 0900 PST Sunday)

 o   ~18 hr. duration

 

Today’s Activities:

 -0700: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

 -0830 – 1130: Preflight of Instruments with Aircraft Power and Data-IT support

 o   Hands off at 1130.

 -0900: T-1 Briefing (Building 18006, Rm 15)

 -1900 – 2200: “Day-of-Flight” Inst. Pre-flight activity

 

Plan for tomorrow, Monday (Science Flight #2):

 -0100: T-0 Briefing (to be held in the GH Crew Area, Hangar)

 o   0145: Staff PMOF

 -0210: Engine Start

 o   0245: Pin-Pull

 - ~0300: Taxi and Take-off

 - ~2100: Landing (18-hr flight)

 -2100 – 0400: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

 o  2130: PCRS, DLH, and UCATS will have post-landing access for Cal. Gas Shutoff

 o   Zone-25 and Z-14 (R2) to be removed temporarily after weighing for this access

The Plan for Tuesday is for Aircraft and Instrument Post-flight:

 -0900 - 1300: Access to instruments with aircraft power and Data-IT support

 o   Avionics Tech will support small panel removal.

 o   Any instrument needing Crew support (MMS, CPL) – start at 1100.