ATTREX 01/13/14 Daily Schedule
ATTREX GH Overview:
- ATTREX Instruments Ready for final pre-flight procedures.
- A/C To PMOF (Guam) Comm Testing Guam successfully accomplished on Jan 9th.
Today's Accomplishments:
- ATTREX air cargo picked up. ETA to Guam: Jan 16th and at AAFB: Jan 17th.
- Ongoing Comm Testing: A/C To GMOF (Guam). Testing to continue on Tuesday, Jan 10th.
Plans for Tuesday, Jan 14 (@ DFRC):
- 0900 – 1130 Instrument teams have power and aircraft access in the hangar.
- 1200 – 1700 Aircraft outdoors for continuation of comm testing with GHMOF in Guam.
- For limited access while the plane is outdoors, please coordinate with Jhony Zavaleta.
Plans for Wednesday, Jan 15th (@ DFRC): (Schedule will be revised as needed)
- 1100 A/C Power On. Instrument teams have aircraft access.
- 1400 Hands off / Power Off
- 1500 Aircraft Roll Out
- 1645 Instrument teams to GHOC
- (User packets will go straight to Guam. Presence in GHOC desired for any questions/troubleshooting by IT prior to launch.)
- 1700 Engine Starts
- 1800 Take Off
TRANSIT FLIGHT PLAN:
- TAKE OFF: from DFRC on Wednesday, Jan 15th, 1800 PST / Thursday, 16th, 1200 ChST (Guam)
- PMOF Staffing in Guam at 1045 for all Instrument Teams
- LANDING: in Guam on Friday, Jan 17th, 0800 CHST / Thursday, Jan 16th 1400 PST