ATTREX 01/13/14 Daily Schedule

ATTREX  GH Overview:
  • ATTREX Instruments Ready for final pre-flight procedures.
  • A/C To PMOF (Guam) Comm Testing Guam successfully accomplished on Jan 9th.
Today's Accomplishments:
  • ATTREX air cargo picked up. ETA to Guam: Jan 16th and at AAFB: Jan 17th.
  • Ongoing Comm Testing: A/C To GMOF (Guam). Testing to continue on Tuesday, Jan 10th.

Plans for Tuesday, Jan 14 (@ DFRC):
  • 0900 – 1130 Instrument teams have power and aircraft access in the hangar.
  • 1200 – 1700 Aircraft outdoors for continuation of comm testing with GHMOF in Guam.
    • For limited access while the plane is outdoors, please coordinate with Jhony Zavaleta.
 
Plans for Wednesday, Jan 15th (@ DFRC): (Schedule will be revised as needed)
  • 1100  A/C Power On. Instrument teams have aircraft access.
  • 1400  Hands off / Power Off
  • 1500  Aircraft Roll Out
  • 1645  Instrument teams to GHOC
    • (User packets will go straight to Guam. Presence in GHOC desired for any questions/troubleshooting by IT prior to launch.)
  • 1700  Engine Starts
  • 1800  Take Off

TRANSIT FLIGHT PLAN:
  • TAKE OFF: from DFRC on Wednesday, Jan 15th, 1800 PST / Thursday, 16th, 1200 ChST (Guam)
    • PMOF Staffing in Guam at 1045 for all Instrument Teams
  • LANDING:  in Guam on Friday, Jan 17th, 0800 CHST / Thursday, Jan 16th 1400 PST