ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 2013 DFRC Campaign
ATTREX 01/16/13 Daily Schedule
1/16 Accomplishments:
Nose gear successfully changed and checked out
Majority of instruments completed preflight preparations
Aircraft preflights
1/17 Plans:
DLH to arrive at the hangar @ 01:00 for instrument preflight
mini-DOAS and HU/PCRS to arrive @ 02:00 for instrument preflights
Engine start @ 05:30
Take-off @ 07:00 for a 4-5 hour range flight
Instrument teams need to be at the GHOC @ 05:00
ATTREX 01/15/13 Daily Schedule
1/15 Accomplishments:
Successful completion of CST
Removal of not leaking nose gear strut from AV-1
Removal of leaking nose gear strut from AV-6
Installation of AV-1 nose gear strut onto AV-6
1/16 Plans:
Perform nose gear strut servicing and complete functional checks
Preflight aircraft for Thursday 07:00 take-off for range flight
Tentative plan is still to perform science flight on Friday
ATTREX 01/14/13 Daily Schedule
1/14 Accomplishments:
The Ku system issues encountered during the attempted CST turned the exercise into a "Pre-CST" which was accomplished with full Ku functionality
After the CST begin repairing aircraft nose strut (leaking) (If it goes well it could take about a day)
1/15 Plans:
CST - Instrument team representatives need to be at the Payload Operations Room in the GHOC @ 08:00
Begin repairing aircraft nose strut (leaking) (If it goes well it could take about a day)