P-3 Orion 03/28/13

Download PDF
Flight Number: 
2013 Operation IceBridge Arctic #1477
Payload Configuration: 
2013 Operation IceBridge Arctic
Nav Data Collected: 
No
Total Flight Time: 
3.3 hours
Flight Segments: 
From:BGTLTo:BGTL
Start:03/28/13 10:55 Z Finish:03/28/13 14:10 Z
Flight Time:3.3 hours
Log Number:13P001PI:Michael Studinger
Funding Source:Bruce Tagg - NASA - SMD - ESD Airborne Science Program
Purpose of Flight:Science
Comments:2013 Operation IceBridge Arctic: Science flight over North Pole Transect. Flight ended early doe to a maintenance issue.
Flight Hour Summary: 
13P001
Flight Hours Approved in SOFRS255
Total Used211.6
Total Remaining43.4
13P001 Flight Reports
Date Flt # Purpose of Flight Duration Running Total Hours Remaining Miles Flown
03/14/132013 Operation IceBridge Arctic #1447Check0.80.8254.2
03/14/132013 Operation IceBridge Arctic #1449Check2.12.9252.1
03/15/132013 Operation IceBridge Arctic #1448Check46.9248.1
03/18/132013 Operation IceBridge Arctic #1450Transit7.914.8240.2
03/20/132013 Operation IceBridge Arctic #1468Science6.321.1233.9
03/21/132013 Operation IceBridge Arctic #1456Transit8.529.6225.4
03/22/13 - 03/23/132013 Operation IceBridge Arctic #1474Science8.237.8217.2
03/23/132013 Operation IceBridge Arctic #1470Science7.845.6209.4
03/24/13 - 03/25/132013 Operation IceBridge Arctic #1469Science8.454201
03/26/132013 Operation IceBridge Arctic #1475Transit8.662.6192.4
03/27/132013 Operation IceBridge Arctic #1476Science7.970.5184.5
03/28/132013 Operation IceBridge Arctic #1477Science3.373.8181.2
04/02/132013 Operation IceBridge Arctic #1486Transit6.480.2174.8
04/04/132013 Operation IceBridge Arctic #1484Science8.188.3166.7
04/05/132013 Operation IceBridge Arctic #1489Science7.896.1158.9
04/06/132013 Operation IceBridge Arctic #1487Science8104.1150.9
04/08/132013 Operation IceBridge Arctic #1491Science7.5111.6143.4
04/09/132013 Operation IceBridge Arctic #1493Science6.4118137
04/10/132013 Operation IceBridge Arctic #1493Science6.6124.6130.4
04/11/132013 Operation IceBridge Arctic #1495Science7.4132123
04/12/132013 Operation IceBridge Arctic #1496Science6.2138.2116.8
04/15/132013 Operation IceBridge Arctic #1502Science7.9146.1108.9
04/18/132013 Operation IceBridge Arctic #1504Transit5.2151.3103.7
04/19/132013 Operation IceBridge Arctic #1505Science7.4158.796.3
04/20/132013 Operation IceBridge Arctic #1508Science6.8165.589.5
04/22/132013 Operation IceBridge Arctic #1512Science7.8173.381.7
04/23/132013 Operation IceBridge Arctic #1513Science7.718174
04/24/132013 Operation IceBridge Arctic #1514Science818966
04/25/132013 Operation IceBridge Arctic #1515Science7.5196.558.5
04/26/132013 Operation IceBridge Arctic #1516Science7.1203.651.4
05/02/132013 Operation IceBridge ArcticTransit7.5211.143.9
05/02/132013 Operation IceBridge ArcticTransit0.5211.643.4

Flight Reports began being entered into this system as of 2012 flights. If there were flights flown under an earlier log number the flight reports are not available online.

Related Science Report: 

OIB - P-3 Orion 03/28/13 Science Report

Mission: 
OIB
Mission Summary: 

F08 Sea Ice - North Pole Transect (aborted)

Science Data Report Summary

Instrument Operated Data Volume Instrument Issues/Comments
ATM yes N/A Was not operated before the flight was aborted.
DMS yes 5 GB None.
Snow Radar yes 3.2 GB None.
Ku-band Radar yes 3.2 GB None.
Accumulation Radar yes 8.0 GB None.
MCoRDS no N/A MCoRDS was not operated due to sea ice mission.
KT-19 yes N/A Was not operated before the flight was aborted.

Mission Report (Michael Studinger, Mission Scientist)

Today's mission was aborted as a safety precaution at the start of the survey line near waypoint NP04. Several instrument teams collected data along the high-altitude transit from Thule Air Base to NP04 over Ellesmere Island. Snow and a low ceiling prevented a ramp pass before landing at Thule Air Base.

Images: