31 |
|||||
«
AirMOSS Mission CR (FR 14G016)
2014-03-24 - 2014-04-02
|
992 Maintenance
2014-04-03 - 2014-04-11
»
|
|||||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
|
|
|
||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
»
|
||||||
«
Remote Sensing Avionics Upgrade
2014-02-03 - 2014-03-31
|
Flight Testing
2014-04-01 - 2014-05-15
»
|
|||||
«
DC-8 at Palmdale SAIF in post Heavy C Check reassembled
2014-03-03 - 2014-04-18
»
|
||||||
«
Maintenance
2014-03-10 - 2014-04-16
»
|
||||||
«
B Check
2014-03-17 - 2014-04-11
»
|
||||||
«
Ship 2 Modifications
2014-03-23 - 2014-07-31
»
|
||||||
«
AirSWOT Cal/Check Flights
2014-02-13 - 2014-05-16
»
|
||||||
«
UAS in the NAS Flight Testing
2014-03-20 - 2014-04-18
»
|
||||||
«
Two-Micron IPDA Lidar Flight Test
2014-03-24 - 2014-04-18
»
|
||||||
«
CALIPSO Cal/Val
2014-03-03 - 2014-04-15
»
|
||||||
«
Operation Ice Bridge
2014-03-10 - 2014-05-23
»
|
||||||
«
H-2 Payload I&T
2014-03-26 - 2014-04-13
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
«
UAS Modifications/Ground Tests
2014-03-01 - 2014-04-30
»
|
||||||
«
ATTREX Download
2014-03-18 - 2014-04-18
»
|
||||||
|
HyspIRI
2014-03-31 - 2014-05-09
»
|
|||||
|
|
|||||
«
Flight Testing
2014-04-01 - 2014-05-15
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
|
IPHEX: CRS Upload
2014-04-09 - 2014-04-13
»
|
|||||
«
DC-8 at Palmdale SAIF in post Heavy C Check reassembled
2014-03-03 - 2014-04-18
»
|
||||||
«
Maintenance
2014-03-10 - 2014-04-16
»
|
||||||
«
B Check
2014-03-17 - 2014-04-11
|
|
|||||
«
Ship 2 Modifications
2014-03-23 - 2014-07-31
»
|
||||||
«
992 Maintenance
2014-04-03 - 2014-04-11
|
|
|||||
«
AirSWOT Cal/Check Flights
2014-02-13 - 2014-05-16
»
|
||||||
«
UAS in the NAS Flight Testing
2014-03-20 - 2014-04-18
»
|
||||||
«
Two-Micron IPDA Lidar Flight Test
2014-03-24 - 2014-04-18
»
|
||||||
«
HyspIRI
2014-03-31 - 2014-05-09
»
|
||||||
«
CALIPSO Cal/Val
2014-03-03 - 2014-04-15
»
|
||||||
«
Operation Ice Bridge
2014-03-10 - 2014-05-23
»
|
||||||
«
H-2 Payload I&T
2014-03-26 - 2014-04-13
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
«
UAS Modifications/Ground Tests
2014-03-01 - 2014-04-30
»
|
||||||
«
ATTREX Download
2014-03-18 - 2014-04-18
»
|
||||||
|
|
Central & South America
2014-04-08 - 2014-05-06
»
|
||||
New Autopilot Phase I Flight Testing
2014-04-08 - 2014-07-03
»
|
||||||
|
|
|||||
«
Central & South America
2014-04-08 - 2014-05-06
»
|
||||||
«
Flight Testing
2014-04-01 - 2014-05-15
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
DC-8 at Palmdale SAIF in post Heavy C Check reassembled
2014-03-03 - 2014-04-18
|
|
|||||
«
Maintenance
2014-03-10 - 2014-04-16
|
|
CARVE California Upload
2014-04-18 - 2014-04-19
|
||||
«
Ship 2 Modifications
2014-03-23 - 2014-07-31
»
|
||||||
«
New Autopilot Phase I Flight Testing
2014-04-08 - 2014-07-03
»
|
||||||
«
AirSWOT Cal/Check Flights
2014-02-13 - 2014-05-16
»
|
||||||
«
UAS in the NAS Flight Testing
2014-03-20 - 2014-04-18
|
|
|||||
«
Two-Micron IPDA Lidar Flight Test
2014-03-24 - 2014-04-18
|
|
|||||
«
HyspIRI
2014-03-31 - 2014-05-09
»
|
||||||
«
CALIPSO Cal/Val
2014-03-03 - 2014-04-15
|
CARVE Transit to Calfornia
2014-04-16 - 2014-04-18
|
|
||||
«
Operation Ice Bridge
2014-03-10 - 2014-05-23
»
|
||||||
«
H-2 Payload I&T
2014-03-26 - 2014-04-13
|
AirMOSS Mission CH/OK (FR 14G016)
2014-04-14 - 2014-04-25
»
|
|||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
«
UAS Modifications/Ground Tests
2014-03-01 - 2014-04-30
»
|
||||||
«
ATTREX Download
2014-03-18 - 2014-04-18
|
|
|||||
«
IPHEX: CRS Upload
2014-04-09 - 2014-04-13
|
ACCESS 2
2014-04-14 - 2014-06-10
»
|
|||||
|
IPHEX: HIWRAP/CRS/EXRAD/LIP Upload
2014-04-14 - 2014-04-19
|
|||||
|
|
|
|
|||
«
Central & South America
2014-04-08 - 2014-05-06
»
|
||||||
«
Flight Testing
2014-04-01 - 2014-05-15
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
Ship 2 Modifications
2014-03-23 - 2014-07-31
»
|
||||||
«
New Autopilot Phase I Flight Testing
2014-04-08 - 2014-07-03
»
|
||||||
«
AirSWOT Cal/Check Flights
2014-02-13 - 2014-05-16
»
|
||||||
«
HyspIRI
2014-03-31 - 2014-05-09
»
|
||||||
«
AirMOSS Mission CH/OK (FR 14G016)
2014-04-14 - 2014-04-25
|
|
|||||
«
Operation Ice Bridge
2014-03-10 - 2014-05-23
»
|
||||||
«
ACCESS 2
2014-04-14 - 2014-06-10
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
«
UAS Modifications/Ground Tests
2014-03-01 - 2014-04-30
»
|
||||||
|
Phase Inspection
2014-04-21 - 2014-05-12
»
|
|||||
Phase Inspection
2014-04-21 - 2014-05-12
»
|
||||||
Post Heavy C Check Systems Checkout and Pilot Proficiency Flights
2014-04-21 - 2014-04-30
»
|
||||||
CARVE Project Check Flights
2014-04-21 - 2014-04-26
|
||||||
IPHEX: COSMIR/AMPR Upload
2014-04-21 - 2014-04-24
|
|
|
||||
TWiLiTE
2014-04-21 - 2014-05-26
»
|
||||||
|
|
|
SLAP Spring 2014 Campaign
2014-04-24 - 2014-06-06
»
|
|||
|
||||||
1 |
2 |
3 |
||||
«
Central & South America
2014-04-08 - 2014-05-06
»
|
||||||
«
Flight Testing
2014-04-01 - 2014-05-15
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
Ship 2 Modifications
2014-03-23 - 2014-07-31
»
|
||||||
«
New Autopilot Phase I Flight Testing
2014-04-08 - 2014-07-03
»
|
||||||
«
Phase Inspection
2014-04-21 - 2014-05-12
»
|
||||||
«
Phase Inspection
2014-04-21 - 2014-05-12
»
|
||||||
«
AirSWOT Cal/Check Flights
2014-02-13 - 2014-05-16
»
|
||||||
«
HyspIRI
2014-03-31 - 2014-05-09
»
|
||||||
«
Post Heavy C Check Systems Checkout and Pilot Proficiency Flights
2014-04-21 - 2014-04-30
|
Annual Inspection
2014-05-01 - 2014-05-30
»
|
|||||
«
Operation Ice Bridge
2014-03-10 - 2014-05-23
»
|
||||||
«
ACCESS 2
2014-04-14 - 2014-06-10
»
|
||||||
«
SLAP Spring 2014 Campaign
2014-04-24 - 2014-06-06
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
«
UAS Modifications/Ground Tests
2014-03-01 - 2014-04-30
|
Local Flights (Prototype DAA Radar)
2014-05-01 - 2014-05-23
»
|
|||||
«
TWiLiTE
2014-04-21 - 2014-05-26
»
|
||||||
|
Ground Crew to WR
2014-04-28 - 2014-04-30
|
ACCESS II Upload
2014-05-01 - 2014-05-05
»
|
||||
UAS in the NAS Flight Testing
2014-04-28 - 2014-05-02
|
IPHEX Deployment Warner Robins
2014-05-03 - 2014-06-16
»
|
|||||
CARVE Transit to Alaska
2014-04-28 - 2014-04-30
|
|
CARVE - Deployment
2014-05-02 - 2014-05-03
|
||||
|
Deconfigure from AirMOSS
2014-04-30 - 2014-05-05
»
|
|||||
Aircraft Upgrades
2014-04-30 - 2014-07-01
»
|
||||||
|
|
|